Fictional worked example. A consultant reviews Eastgate Fulfilment for Marlow Retail for October 2026. The client supplies its 0–5 assessment ratings and weights. The proposed working rubric is 0 = not delivered, 1 = severe shortfall, 2 = material shortfall, 3 = minor shortfall, 4 = meets expectations and 5 = exceeds expectations; KPI-specific thresholds still need agreement. September and October ratings use the same scope and definitions. No supplier response has yet been obtained.

The client question: What should the client address with its existing supplier, and what can the available evidence support?

Supplier scorecard: the working record
KPI / weightOctober evidence and supplied ratingSeptember rating / review implication
On-time delivery / 4092% of 200 dispatches against a 98% target; client rating 3/5. Dispatch log reported by the consultant.4/5; performance rated lower. Investigate exceptions before asserting a cause.
Order accuracy / 3099.5% of 200 orders against a 99.5% target; client rating 4/5. Returns reconciliation reported.4/5; no rating change on the declared common basis.
Support response / 20Support log not supplied; rating unknown. Do not score zero or assume the SLA was met.Unknown; obtain the log and agreed timing definition.
Invoice accuracy / 10All 20 checked invoices correct; client rating 4/5. Sample does not establish all invoices were correct.4/5; retain the sample boundary.
Critical dispatch requirement / outside averageTwo missed priority dispatches reported against a stated zero-miss critical requirement.Critical issue requires review regardless of the weighted score; this is not a legal finding.
Calculated result80% weighted evidence coverage. Provisional rated-only score 70/100; no complete overall score.Matched 80% of weight: down 10 points. This is not an overall supplier trend.

Make the calculation reproducible.

The scored weight is 40 + 30 + 10 = 80. Weighted ratings are (40 × 3) + (30 × 4) + (10 × 4) = 280. The rated-only result is 280 ÷ 80 ÷ 5 × 100 = 70. These are rating points, not the percentage of obligations met. The unscored support measure prevents a complete total.

Keep missing evidence and critical issues visible.

Support carries 20% of the weight. Missing its log is an evidence gap, not proof of poor service. Separately, the reported priority-dispatch misses need escalation and a response; a positive average cannot erase them.

Compare the same measures.

Using the same weights, September scores 80/100 on the matched delivery, accuracy and invoicing criteria; October scores 70. The 10-point decline applies only to that matched 80% of weight. It is not a comparison of complete supplier performance.

Close the review with owned actions.

Propose a joint exception review and immediate containment for priority dispatches. Ask the supplier account lead for the support log and response, with owners and dates to agree. Close actions only when the agreed evidence is supplied and reviewed. Do not treat a proposed recovery plan as accepted.

The next client decision

Agree a recovery discussion and evidence request, confirm the KPI-specific rating thresholds, and set the next review. Recalculate when the support rating is evidenced. No renewal, termination or payment decision is authorised by the scorecard.

What to bring to your own review

A mistake to avoid

Do not hide an unmeasured KPI by removing its weight, turn unknown into zero, or use a healthy average to dismiss a critical service issue.