Northbank: the CRM launched, but are the benefits reaching the team?
Prepared by Practice. Fictional teaching example; not client data or achieved results.
Use your browser’s Print command to save a PDF. Read the example and open the free tool.
A consultant reviews a fictional CRM rollout at Northbank Advisory, 12 weeks after go-live. The system launched on its planned date. The sponsor wanted consistent client handoffs, weekly use by at least 24 of 30 account managers by week 12, and less time preparing pipeline reports. The findings below are illustrative supplied evidence, not real client results.
The client question: Should the sponsor close the project, or keep a bounded improvement and benefits-review plan open?
| Objective and original target | Evidence at week 12 | Review judgement and proposed next step |
|---|---|---|
| Launch on the agreed date. | Project record reports launch on the planned date. Final implementation cost was not supplied. | Timing achieved as reported. Budget performance remains unknown; this does not establish adoption or benefits. |
| At least 24 of 30 account managers use the CRM weekly by week 12. | Usage export records 18 of 30 users during week 12. It measures logins, not completed client handoffs. | Weekly usage is below the stated target. Inspect representative handoffs before judging effective adoption. |
| Reduce weekly pipeline-report preparation from a recorded baseline of four hours to two hours by week 12. | Operations estimates three hours for the week-12 report; no comparable time log has been collected. | The estimate suggests progress, but target achievement and sustained savings are not established. Log the same reporting tasks for four weeks. |
| Create consistent client handoffs; no numerical target supplied. | A consultant reviewed 20 handoffs from weeks 9–12; seven lacked the agreed next-action field. Sampling method was not supplied. | A gap is evidenced in the reviewed sample. Do not apply that rate to all handoffs or infer a training cause. Inspect the workflow with users. |
| Retire duplicate reporting; original deadline not supplied. | The operations lead reports that the weekly pipeline spreadsheet is still maintained. | Confirm why it remains necessary before changing the process. Retirement is a proposed decision, not an agreed or completed action. |
Keep delivery and benefits separate.
The launch date answers whether a milestone was met. It does not answer whether the team is using the workflow or whether reporting has improved. The usage record shows 18 weekly users against a target of 24, both out of 30. Even reaching that target would establish recorded usage, not complete or accurate client work.
Explain what each source can support.
The reporting estimate and historical baseline may have been collected differently, so they cannot establish a verified time saving. The handoff review identifies seven omissions among 20 reviewed records; it does not establish the rate across the firm. Ask how records were selected and whether the required field and review standard were consistent.
Turn findings into small, testable actions.
Propose that the CRM owner and operations lead inspect five recent handoffs with users in the next fortnight, then agree whether the response is workflow, access, guidance or training. Ask operations to record reporting effort for four weeks. These are suggested roles and timings for sponsor approval, not existing commitments or proof of the cause.
The next client decision
Ask the sponsor to approve a four-week follow-up: confirm action owners, examine the incomplete handoffs, gather comparable reporting-time evidence and review meaningful use. Keep benefits ownership open until the sponsor has enough evidence to decide on closure. Do not describe the whole project as a failure or claim verified ROI.
What to bring to your own review
- The original project objectives, agreed targets, go-live date and review period.
- Usage records, work samples, cost records and feedback, with sources and known limitations.
- The sponsor decision needed, existing action owners and benefits that require later follow-up.
A mistake to avoid
Treating a successful launch as proof of benefits, turning login counts into effective adoption, or presenting an estimate as verified savings.