Westhaven Services: a delayed migration and a decision for the sponsor

Prepared by Practice. Fictional teaching example; not client data or achieved results.

Use your browser’s Print command to save a PDF. Read the example and open the free tool.

Fictional worked example. A consultant is reporting a CRM rollout for Westhaven Services as of 24 November 2026. The approved project budget is £60,000; reported actual spend is £48,000 and forecast total cost at completion is £62,000, on the same GBP cost basis. Design sign-off was completed on its 20 November baseline date. Migration is incomplete: baseline 27 November, current forecast 4 December. User acceptance testing has not started: baseline 4 December, forecast 11 December. Launch remains forecast for its 18 December baseline date but is at risk if testing or sign-off is delayed. The delivery lead reports duplicate records blocking migration. The sponsor has not approved an additional £2,000; a decision is requested by 27 November. No overall RAG rating, percent-complete measure or approved rebaseline was supplied.

The client question: What has changed, what is at risk, and what must the sponsor decide now?

Project status report: the working record
AreaReported position at 24 November 2026Interpretation / next check
Design sign-offBaseline 20 Nov · actual 20 NovReported complete; no date variance.
MigrationBaseline 27 Nov · forecast 4 Dec7 calendar days later; incomplete, not an actual completion.
User acceptance testingBaseline 4 Dec · forecast 11 Dec7 calendar days later; not started.
LaunchBaseline and forecast 18 DecDate retained, but at risk; not a confirmed successful launch.
Cost forecast£48,000 actual · £62,000 forecast total · £60,000 approvedForecast £2,000 above budget (3.33%); £14,000 forecast remaining.
Client decision£2,000 additional budget requested by 27 NovNot approved. Keep the approved budget at £60,000.

Keep dates and confidence separate.

Migration and testing forecasts are seven calendar days later than their baselines. The launch forecast remains 18 December, but that does not establish the date is secure. Keep its testing and sign-off dependencies visible.

Compare total forecast with approved budget.

£62,000 forecast total less £60,000 approved budget gives a £2,000 forecast overrun, or 3.33%. £62,000 less £48,000 actual spend gives £14,000 forecast remaining. Do not add actual spend to the total forecast.

Put the client decision near the front.

The sponsor needs to decide on the requested £2,000 by 27 November. This request is not an approved budget change. Clarify the effect of refusal or delay with the delivery lead rather than inventing a guaranteed launch outcome.

Update the whole report next time.

In a later update, preserve the original baselines and change all affected forecasts, totals and decisions together. Keep unresolved issues and unapproved requests open; label carried-forward information that has not been revalidated.

The next client decision

Ask the sponsor to decide on the £2,000 request by 27 November and confirm migration recovery ownership and testing capacity. Keep the approved budget and original milestone baselines unchanged until an authorised change is supplied.

What to bring to your own review

A mistake to avoid

Calling the project 80% complete because 80% of its budget has been spent, or treating a requested budget increase as approved.