Make progress clear.
Make the next decision easy.

Turn scattered project notes into a clear report for your client or sponsor. Show what moved, what is at risk and which decisions are needed. Build the pages through conversation, then update them as the project changes.

Build your status report

Free to use · No account required · PDF & Word downloads

Download the editable Word template

Start with your brief.

Describe the client situation and the evidence you have. The guide asks for the details needed to shape your document.

Make the pages your own.

Use the starting template, then change the writing, tables, diagrams and page layout through conversation.

Take a useful document away.

Apply the changes you want and download a designed PDF or editable Word version. Review it before using it with a client.

The method

What is a
project status report?

A project status report is a dated account of delivery progress, milestones, costs, issues, risks and decisions needed. It compares the original plan with current forecasts and actual results. This builder helps a consultant prepare and update a client-facing document; it does not connect to project systems or monitor progress automatically.

  1. 01

    Set the reporting boundary.

    Name the project, audience, reporting period and as-of date. Identify what changed since the previous update.

  2. 02

    Separate plan, forecast and actual.

    Retain original milestone dates. Show forecasts as forecasts and completion only when the evidence supports it.

  3. 03

    Explain the money and the risk.

    Compare total forecast cost with approved budget. Keep current issues distinct from risks that may occur; do not infer completion from spending.

  4. 04

    Make the client’s decision explicit.

    State the request, owner, needed-by date and consequence of delay. Carry unresolved decisions forward when you update the report.

Worked example / Project status report

Westhaven Services: a delayed migration and a decision for the sponsor

Fictional worked example. A consultant is reporting a CRM rollout for Westhaven Services as of 24 November 2026. The approved project budget is £60,000; reported actual spend is £48,000 and forecast total cost at completion is £62,000, on the same GBP cost basis. Design sign-off was completed on its 20 November baseline date. Migration is incomplete: baseline 27 November, current forecast 4 December. User acceptance testing has not started: baseline 4 December, forecast 11 December. Launch remains forecast for its 18 December baseline date but is at risk if testing or sign-off is delayed. The delivery lead reports duplicate records blocking migration. The sponsor has not approved an additional £2,000; a decision is requested by 27 November. No overall RAG rating, percent-complete measure or approved rebaseline was supplied.

Prepared by Practice. Fictional teaching example; not client data or achieved results.

The client questionWhat has changed, what is at risk, and what must the sponsor decide now?

Project status report: the working record
AreaReported position at 24 November 2026Interpretation / next check
Design sign-offBaseline 20 Nov · actual 20 NovReported complete; no date variance.
MigrationBaseline 27 Nov · forecast 4 Dec7 calendar days later; incomplete, not an actual completion.
User acceptance testingBaseline 4 Dec · forecast 11 Dec7 calendar days later; not started.
LaunchBaseline and forecast 18 DecDate retained, but at risk; not a confirmed successful launch.
Cost forecast£48,000 actual · £62,000 forecast total · £60,000 approvedForecast £2,000 above budget (3.33%); £14,000 forecast remaining.
Client decision£2,000 additional budget requested by 27 NovNot approved. Keep the approved budget at £60,000.

Keep dates and confidence separate.

Migration and testing forecasts are seven calendar days later than their baselines. The launch forecast remains 18 December, but that does not establish the date is secure. Keep its testing and sign-off dependencies visible.

Compare total forecast with approved budget.

£62,000 forecast total less £60,000 approved budget gives a £2,000 forecast overrun, or 3.33%. £62,000 less £48,000 actual spend gives £14,000 forecast remaining. Do not add actual spend to the total forecast.

Put the client decision near the front.

The sponsor needs to decide on the requested £2,000 by 27 November. This request is not an approved budget change. Clarify the effect of refusal or delay with the delivery lead rather than inventing a guaranteed launch outcome.

Update the whole report next time.

In a later update, preserve the original baselines and change all affected forecasts, totals and decisions together. Keep unresolved issues and unapproved requests open; label carried-forward information that has not been revalidated.

The next client decision

Ask the sponsor to decide on the £2,000 request by 27 November and confirm migration recovery ownership and testing capacity. Keep the approved budget and original milestone baselines unchanged until an authorised change is supplied.

Download the full example (HTML)Download the example table (CSV)

Read the HTML copy in your browser or print it to PDF. The CSV contains the table, ready to adapt in a spreadsheet.

What to bring to your own review

  • Project, client, as-of date and reporting period.
  • Original milestone dates, current forecasts and actual completion or acceptance evidence.
  • Approved budget, spend to date and a clearly defined total or remaining forecast.
  • Issues, risks, unresolved decisions, owners and needed-by dates.

A mistake to avoid

Calling the project 80% complete because 80% of its budget has been spent, or treating a requested budget increase as approved.

Use the free project status report tool

Before you begin

A few useful
answers.

You can download the Word template directly or open the builder and start with a short description.

Is this a free project status report template?

Yes. Download the editable Word template or use the chat builder without an account, within fair-use limits. The landing page includes a fictional worked example.

Who is this builder for?

Consultants, project leads and PMO teams preparing a client or sponsor update during delivery. It is designed for a useful decision conversation, rather than a generic progress summary.

Can I update last week’s report?

Yes. Continue your saved draft in the same browser or paste the previous report into the chat, then explain the new reporting date and changes. Review proposed edits before applying them. This is a manual update workflow, not scheduled monitoring or a project-system integration.

Does it decide whether the project is red, amber or green?

It can use the status and rules you supply, or propose a clearly labelled rating for review. It does not treat spend or elapsed time as percent complete and does not invent an agreed status.

Can it calculate budget and milestone variances?

Yes. A checked calculation tool compares approved budget, actual spend and total forecast on a common currency/cost basis, and compares milestone dates in calendar days. Unknowns remain unknown. These calculations do not verify source data or predict delivery success.

What if information is missing?

The guide can build a draft with visible gaps and ask focused questions. It should not invent completion, approval, owners or financial figures to make the report look finished.

Can it research and cite sources?

The guide has shared web search and source-reading tools for public methods or context when useful. Public sources cannot establish the facts of your project; supply those yourself and review citations.

What can the AI change?

The guide works with the actual document pages. It can propose new writing, tables, diagrams, page layouts or page order. Preview its changes, then apply them or keep the current document. You can undo an applied update.

What can I download?

Download a PDF that preserves the designed pages or a Word document with editable text and tables. Word uses simpler formatting and includes diagrams as figures. Downloads contain the applied document and exclude the chat. The free starting Word template is available above.

Where are my draft and conversation saved?

The current draft and recent conversation are saved on this device for up to seven days. Each tool has its own draft. Sending a message shares the document and recent chat with DeepSeek through DeepInfra for AI processing. Leave out confidential or personal information. Download your document to keep a copy.

How do I use this work in Practice?

Download the document, then add it to a client project in Practice. The free tool does not automatically transfer the draft or conversation into an account.

Ready to begin

Bring your brief.
Build the client document.

Build your status report