Project handover template

Transfer ownership.
Keep the open work visible.

Give the receiving team the evidence, access and support it needs to take over.

Orra Arts handover hub showing deliverable checks and readiness for acceptance
Fable Bureau × Orra Arts · Example handover

Worked acceptance review

The pack has arrived.
Can the team take over?

  • 12 of 18 checks clear
  • 2 of 6 deliverables fully clear
  • 2 open blockers

Orra’s reporting definitions are ready for review, but the team has yet to confirm its escalation rota and support coverage. Hold acceptance in this example until those two gaps are resolved. Keep the lower-priority knowledge base search check assigned to the front-of-house lead.

The receiving team's checks

Review the evidence.
Try the handoff.

Check a deliverable with the person who will use it. Ask them to find the right version and walk through an ordinary task and one exception.

Reporting definitions · ready to review

The operations analyst has checked definitions, confirmed ownership and tested daily reconciliation. Attach the test record to the acceptance pack.

Exception runbook · escalation rota open

The duty manager confirms a primary and backup before rehearsing a duty handoff. Record the owner, date and evidence of that rehearsal.

Support handoff · coverage open

The operations director names who receives incidents and agrees how an urgent issue is escalated. Ask the receiving team to test that contact route.

The acceptance record

Record what passed.
Name who takes over.

  1. List each deliverable, its final version, location, receiving owner and agreed acceptance criteria.
  2. Check access as the receiving team and capture the result of a practical walkthrough.
  3. Separate blockers from follow-up actions. Assign every open item an owner, date and evidence needed to close it.
  4. Record the authorised client decision and confirm the support route, escalation contact and next review.

Useful answers

Before you
begin.

Who should sign off a project handover?

Use the authorised client decision maker agreed in the engagement. Ask the operational owner to confirm readiness and make sure any open actions have named owners and dates.

Can the team accept with open items?

Follow the agreed acceptance criteria. Where conditional acceptance is allowed, identify the open items, owners, dates and consequences explicitly. Resolve any item that prevents safe or usable operation before accepting.