Project handover template
Transfer ownership.
Keep the open work visible.
Give the receiving team the evidence, access and support it needs to take over.

Worked acceptance review
The pack has arrived.
Can the team take over?
- 12 of 18 checks clear
- 2 of 6 deliverables fully clear
- 2 open blockers
Orra’s reporting definitions are ready for review, but the team has yet to confirm its escalation rota and support coverage. Hold acceptance in this example until those two gaps are resolved. Keep the lower-priority knowledge base search check assigned to the front-of-house lead.
The receiving team's checks
Review the evidence.
Try the handoff.
Check a deliverable with the person who will use it. Ask them to find the right version and walk through an ordinary task and one exception.
Reporting definitions · ready to review
The operations analyst has checked definitions, confirmed ownership and tested daily reconciliation. Attach the test record to the acceptance pack.
Exception runbook · escalation rota open
The duty manager confirms a primary and backup before rehearsing a duty handoff. Record the owner, date and evidence of that rehearsal.
Support handoff · coverage open
The operations director names who receives incidents and agrees how an urgent issue is escalated. Ask the receiving team to test that contact route.
The acceptance record
Record what passed.
Name who takes over.
- List each deliverable, its final version, location, receiving owner and agreed acceptance criteria.
- Check access as the receiving team and capture the result of a practical walkthrough.
- Separate blockers from follow-up actions. Assign every open item an owner, date and evidence needed to close it.
- Record the authorised client decision and confirm the support route, escalation contact and next review.
Useful answers
Before you
begin.
Who should sign off a project handover?
Use the authorised client decision maker agreed in the engagement. Ask the operational owner to confirm readiness and make sure any open actions have named owners and dates.
Can the team accept with open items?
Follow the agreed acceptance criteria. Where conditional acceptance is allowed, identify the open items, owners, dates and consequences explicitly. Resolve any item that prevents safe or usable operation before accepting.