Vendor evaluation template
Shortlist with
clear evidence.
Compare suppliers and explain what would change your recommendation.
Follow a worked selection for a work-order platform. Check the mandatory requirements, test the weights and turn the results into a decision the client can review.

The baseline decision
Two for a pilot.
One with an open question.
Beacon edges Aster by a single point. Both clear the mandatory requirements, so the practical next step is a common pilot. Cinder needs to demonstrate usable record export and finish the support assessment.
- Beacon Systems
- 74 / 100
- Test the faster implementation path.
- Aster Supply
- 73 / 100
- Test the stronger workflow fit.
- Cinder Works
- 73–88 / 100
- Score range. Export check pending.
Interactive selection studio
Change the priorities.
See what moves.
Switch from Balanced priorities to Workflow depth and watch Aster move ahead of Beacon. Toggle Only gate-clear candidates to see which suppliers are eligible to advance.
Run your own evaluation
Give each supplier
the same brief.
Use the editable template to record gates, scores, source evidence and follow-up. Open the CSV in your spreadsheet app and add one row per vendor and requirement.
Download the shortlist template (CSV)Agree what every vendor must meet
Write each mandatory requirement as a check someone can perform. For a usable export, specify the fields and format you need. Ask each vendor to produce the same sample. Mark the result pass, fail or pending.
Score the same tasks on the same scale
Define what a 1, 3 and 5 look like for each criterion. Give vendors the same work order and exception scenario. Link every score to what you saw, and leave a score blank until you have evidence.
Compare the cost over the same period
Line up licence costs, implementation, internal effort, support and exit costs over the same term. Note any assumptions about volumes and included services. A cheaper quote may cover less work.
Test the ranking before recommending
Try a second set of weights that reflects a plausible change in priorities. If it changes the leader, name what drove the change and design a pilot that can resolve the trade-off.
For more on testing whether a ranking holds when priorities change, see HM Treasury’s guidance on sensitivity analysis.
Have your criteria and evidence ready? Compare your own shortlist in Practice.
Open the Weighted Decision MatrixUseful answers
Before you
begin.
How do I calculate a weighted vendor score?
Give each criterion a weight and score each vendor on the same scale. With scores out of five, multiply the score divided by five by its percentage weight, then add the contributions. For example, 4 out of 5 on a criterion worth 30% contributes 24 points out of 100.
What if a vendor has missing evidence?
Keep the criterion open and record what would resolve it. If you show a score range, explain how much of it comes from unassessed criteria. Keep an unresolved mandatory requirement marked pending until someone checks it.
How is a vendor evaluation different from a supplier scorecard?
Use vendor evaluation to decide whom to select. After appointment, use a supplier scorecard to review performance against agreed expectations using actual delivery evidence.